Open the editor

Economics · University

NPV and IRR Slides

Free animated slides, ready to teach: 6 slides where every step appears on a click and the diagrams move. Play them right here, present them full screen, or copy them into your account to edit.

A real Tracé deck playing in your browser. No account needed.

What the lesson covers

Net present value adds up a project's future cash flows in today's money and subtracts the cost. Students discount three years of returns, slide along the NPV curve to find the internal rate of return and decide whether to invest.

The slides, one by one

1 Net present value and IRR

Is the investment worth it?

Pay £1,000 now to get £400 a year for 3 years. Good deal?

2 Discount each cash flow back to today

NPV = -C_0 + \sum_t \dfrac{C_t}{(1 + r)^t}

£400 a year at 8%, in today's £

3 NPV falls as the discount rate rises

Cost £1,000, then £400 for 3 years

Live graph: y = -1000 + 400/(1 + x) + 400/(1 + x)² + 400/(1 + x)³

IRR: where NPV = 0, about 9.7%

4 Should the firm invest?

A machine costs £1,000 and earns £400 at the end of each of the next 3 years. The discount rate is 8%. Find the NPV.

→ Discount each year's £400, add them, subtract the cost

\dfrac{400}{1.08} \approx 370.37
\dfrac{400}{1.08^2} \approx 342.94
\dfrac{400}{1.08^3} \approx 317.53
NPV \approx 1030.84 - 1000 = 30.84

NPV ≈ £30.84 > 0, so the machine is worth buying

5 Quick check

A project's IRR is 12% and the firm borrows at 9%. It should…

  • Accept: IRR is above the cost
  • Reject: IRR is too high
  • Reject: NPV is negative
  • Wait until IRR is 9%
Show the answer

Accept: IRR is above the cost

At 9% the NPV is positive because 9% is below the 12% IRR.

6 What to remember

Money later is worth less than money now

NPV = -C_0 + \sum C_t/(1 + r)^t

Invest if NPV > 0

IRR: the rate where NPV = 0

Challenge: Why can NPV and IRR rank two projects of different sizes differently?

Every slide is built click by click: text, formulas and pictures come in one step at a time, so the class follows the reasoning instead of reading ahead. Graphs with sliders can be dragged live while you present.

Make your own version with AIChange the level, the numbers or the language: type the topic and get a new deck that moves in about 30 seconds. Free, no account needed.

Questions teachers ask

What is the difference between NPV and IRR?

NPV is the value today of all cash flows at a chosen discount rate; invest if it is positive. IRR is the discount rate that makes NPV zero; invest if it is above the cost of capital.

Are these slides really free?

Yes. Watch them on this page or present them full screen with no account. Making your own copy to edit is free too.

Can I change the slides before my lesson?

Yes. Press "Make my own copy" and the deck becomes one of your projects in the Tracé editor, where you can change the text, the numbers, the colours or the order of the clicks.

Do they work on a classroom projector or an interactive whiteboard?

Yes. They run in the browser on any laptop, so anything that shows your screen works. Press the right arrow or click to go to the next step.